People Mover

Transfer between two Airport terminals
[cable liner system | DCC]

Application
Transfer between two Airport terminals [cable liner system | DCC]

Country

Canada

City

Toronto

Representative office

Conductix-Wampfler [USA]

Operator

Doppelmayr [DCC]

Customer
Siemens, Austria

Technical requirement[s]

Electrification of the interior equipment of the People Mover

Product[s]

Conductor Rail, Hevi-Bar II

Number of [Load]
6

Travel distance [Load]

2 x 1473 m

Travel speed [Load]

43,2 km/h

Number of poles

3 + PE

Collector assembly

Double collector

Current

150 A

Voltage

480 V [AC]

Additional information

  • In operation: 22 hrs./day
  • System capacity: 2150 passengers per hour/direction